The Pending Employee Tasks screen shows the activities that have been scheduled for that day.  You can edit any of these tasks from here as well as set a one time task.  One time tasks that are entered here appear immediately at the designated time and do not require 24 hours to display.

Select Scheduling from the main menu

Image Added

Select Pending Employee Tasks

Image Added

Add a task and the scheduled start and complete dates.  Click "Add".

FieldDescription
Task DescriptionDescription of the Task
Scheduled Start and Complete DateThe time frame the task should be completed within